Fwd: [MCNPARK] Block A new waterproofing - last round of work


Dear all

The new waterproofing for Block A has almost reach end stage.  At this period, the workers are closing up the slab with new cement rendering increasing the height of 4" .  From unit 1 to unit 8 including the tank area.  After fully cementing the place, he will carry out one more round of water ponding for another one day to test the end result.

We will approach the affected residents for their feedback, should there be no leakages occur be it new or old seepage, i think the contractor - Hosen has delivered his work diligently. However, he will still attend to the complain of the same nature as the warranty is valid for two years after completion.

I will invite him to come for this coming meeting to let everybody recognise him or may be have some interview on him.

Thank you

Shirley